Email

rdd@dijuliolaw.com

Monday - Sunday

9:00am - 6:30pm

Project Delays & Change Orders

Construction Law

Construction Delay & Change Order Attorney — Los Angeles

Delay claims are won on the schedule and the notice file. Who caused the delay matters far less than who documented it, and whether the contract permitted recovery at all.

The Short Answer

Can a contractor recover damages for delay in California?

It depends on the contract and the cause. Excusable and compensable delays caused by the owner or its agents generally support recovery of extended overhead, escalation, and disruption costs, provided contractual notice was given. Concurrent delay may limit recovery to time without money. Many private contracts contain no-damages-for-delay clauses, which California courts will enforce subject to recognized exceptions.

Construction Law

Schedule, Notice, and Change Order Disputes

Delay claims turn on the critical path. A delay to work that had float generally causes no compensable harm; a delay to a critical activity pushes completion and generates real cost. Establishing that distinction requires the baseline schedule, the updates as the project progressed, and a defensible analysis of what actually drove the finish date — which is why projects with poor scheduling records rarely produce successful delay claims regardless of the underlying facts.

Notice is the second gate. Nearly every construction contract requires written notice of a delay or change within a short period after the triggering event, and requires cost and time impacts to be submitted in a defined form. Courts do enforce those provisions. A contractor who directs its crews to work through an impact and prices the claim at the end of the job is in a materially weaker position than one who papered it in real time.

Change orders raise the mirror-image problem: work directed in the field, performed, and disputed later. The analysis looks at whether the contract required written authorization, whether the owner's conduct waived that requirement, and whether the work was truly extra or already within the base scope. These issues run directly into payment disputes and are governed by the contract terms negotiated at the outset.

Office

330 North Brand Boulevard, Suite 1280
Glendale, California 91203

Courts

Los Angeles County Superior Court, including the Glendale and Stanley Mosk courthouses.

Focus

Construction contracts, payment and lien claims, defects, delays, and project litigation for owners and contractors.

What We Handle

Delay and Change Order Matters We Handle

For owners, developers, general contractors, and subcontractors on Southern California projects.

Critical Path Delay Claims

Establishing or rebutting delay through baseline and as-built schedule analysis, float ownership, and concurrent delay allocation.

Extended Overhead & Escalation

Field and home office overhead during a compensable delay, material and labor escalation, and equipment standby costs.

Disruption & Loss of Productivity

Out-of-sequence work, trade stacking, and inefficiency claims, which require different proof than pure delay claims.

Acceleration Claims

Directed and constructive acceleration where a contractor is required to recover time it did not cause, including overtime and added crews.

Liquidated Damages

Enforcing and challenging liquidated damages provisions, including proportionality, apportionment for owner-caused delay, and substantial completion arguments.

Change Order Disputes

Directed and constructive changes, differing site conditions, cardinal change, and pricing of extra work performed without a signed change order.

Situations We See

Schedule Disputes That Reach Our Office

Composite examples drawn from the kinds of matters this practice handles. They illustrate common fact patterns and are not descriptions of specific client cases or predictions of any result.

01

The Late Design Package

An owner's design team issues revised structural drawings months into construction. The contractor absorbs the impact, finishes late, and is assessed liquidated damages. Recovery depends almost entirely on whether contemporaneous notice and schedule updates were maintained.

02

The Differing Site Condition

Excavation on a Los Angeles infill site encounters undocumented fill and buried structures. Whether the additional cost is recoverable turns on the contract's differing site conditions clause, the geotechnical report, and the timing of notice.

03

The Change Order Backlog

Forty change order requests remain unsigned at substantial completion while the work has all been performed. The claim is resolved on the written record: what was directed, by whom, and what the contract required.

When to Get Advice

When Delay Issues Need a Lawyer

  • The project has slipped and no one has issued written notice of the cause.
  • Liquidated damages are being assessed or threatened.
  • You have been directed to accelerate to recover time you did not cause.
  • Change order requests are being performed but not approved.
  • A differing site condition has been encountered and priced.
  • The contract contains a no-damages-for-delay clause and you are being delayed.
Practical Next Steps

What to Do First

  1. Give written notice now

    Even a short, dated letter identifying the event and reserving rights preserves a claim that silence forfeits. Notice provisions are enforced.

  2. Preserve the schedule record

    Baseline, updates, daily reports, and manpower logs are the evidence. Reconstructed schedules prepared after the fact carry far less weight.

  3. Price impacts contemporaneously

    Track the cost of each impact as it occurs rather than assembling a total-cost claim at the end, which California courts view skeptically.

Common Questions

Project Delays & Change Orders — Questions California Clients Ask

What contractors and owners ask about delay damages, acceleration, and disputed change orders.

Who is responsible for project delays in California construction?

Responsibility for delays depends on the cause. Owner-caused delays — such as design changes, late approvals, or site access issues — can support contractor claims for additional time and compensation. Contractor-caused delays may entitle the owner to liquidated damages. Concurrent delays can complicate the analysis significantly.

What is a time extension claim in California construction?

A time extension claim is a contractor's request to extend the contractual completion date due to circumstances beyond the contractor's control — such as owner-caused delays, differing site conditions, permit delays, or force majeure events. Properly documented and timely submitted extension claims are critical to avoiding liquidated damages exposure.

What is an acceleration claim?

An acceleration claim arises when a contractor is required to complete work faster than originally planned — either expressly, when the owner orders it, or constructively, when the owner denies a legitimate time extension, effectively forcing the contractor to spend more to finish on schedule. Both types of acceleration can entitle the contractor to additional compensation.

What is a constructive change order?

A constructive change order refers to additional work or costs imposed on a contractor by the owner's conduct — such as owner interference, differing site conditions, defective specifications, or unreasonable rejection of acceptable work — even without a formal written change order. Contractors can seek compensation for constructive changes through the claims process.

How should change orders be handled to avoid disputes?

Change orders should be documented in writing, signed by both parties, and agreed to before the work is performed whenever possible. The change order should clearly describe the scope of work, the price adjustment, and any schedule impact. A clear change order process in the original contract is the best way to minimize change order disputes.

What is notice to proceed and why does it matter?

A notice to proceed (NTP) is the owner's written directive authorizing the contractor to begin work, typically triggering the start of the contract schedule. Changes to the project start can affect completion milestones, float calculations, and delay analyses. Contractors should not start work without written confirmation of the NTP date.

What is float in a project schedule and who owns it?

Float (or "slack") is the amount of time a non-critical activity can be delayed without delaying the project's completion. Whether the contractor or the owner is entitled to consume project float — and the consequences of doing so — depends on the contract language and is frequently disputed in delay claims.

When should I involve an attorney in a construction delay dispute?

You should consult an attorney early — before responding to delay notices, before submitting or denying delay claims, and before signing any change order that includes a release of delay claims. Early legal involvement helps ensure that required notices are timely given and that your position is preserved for potential litigation.

DiJulio Law Group

Talk to a Construction Attorney

The strength of a delay claim is largely fixed by what was documented while the delay was happening. If a project is slipping now, get the notice right today.